For the past three years, the supply chain has been a rollercoaster for the architectural, engineering, and construction (AEC) industries — facing challenges, such as manufacturing disruptions, labor shortages, logistical issues, demand fluctuations, supply chain complexity, and regulatory hurdles. Some of these supply chain issues have been addressed, leading to a more stable and predictable environment for the AEC industry.
While some supply chains have indeed stabilized, it's important to highlight that the health care supply chain still grapples with critical challenges, particularly in the realm of switchgear packages and generator packages. These pieces of equipment are experiencing extended lead times, and the associated low-voltage power circuit breakers, in particular, are facing the longest delays, often surpassing a year from the time a purchase order is issued.