ROOT Data Center Inc. Announces Accelerated Colocation Build Schedule
The next facility will be built in Montreal.
ROOT Data Center Inc. has announced that it has started construction on its next generation, Tier 3 colocation facility in Montreal, Canada. Significant customer demand has required ROOT to accelerate their build schedule. Customers will now have a clean data center floor space to start staging equipment in as early as mid-June 2014. Long lead time equipment was ordered in early to mid-April. Thanks to partnerships with equipment manufacturers and suppliers, such as Eaton, Kyoto Cooling, DL Custom, Gal Power and others, equipment will start arriving on site in mid-May.
"We are encouraged by the stronger than expected customer demand coming from the US and other markets across Canada and overseas. Our value proposition seems to be resonating well with a large array of customers and our construction team and suppliers have been extremely supportive in helping us accelerate our build timelines" Said CEO Jason van Gaal.