The project was guided by the company’s Massively Modular® data center engineering approach.
CyrusOne recently commissioned its fourth company data center — the Houston West site — which was completed in seven months from groundbreaking to commissioning as part of its Massively Modular® facility design strategy.
The company broke ground on the Houston West facility in September 2012 and will complete the project this month. Other recent quick-build sites included Phoenix, and San Antonioand Carrollton, TX. Ground was broken in Phoenix on May 16, 2012, and was commissioned in December 2012. San Antonio and Carrollton broke ground in December 2011 and January 2012 respectively, with both sites completing in July 2012.