Facilities operated by public entities
such as public housing authorities (PHAs) have the same physical
needs as facilities owned privately but are subject to legal
requirements that inhibit their flexibility to upgrade their energy
facilities and address emergency energy-loss situations. This is
because PHAs are public bodies formed by municipalities and governed
by state statutes but are also regulated by the United States
Department of Housing and Urban Development (HUD).
PHA
facilities exist in cities throughout the United States and provide
affordable housing for families. PHAs typically include diverse
structures such as multifamily apartment buildings, meeting
locations, sports facilities, administrative offices, district energy
electric or thermal plants, garages, and other facilities necessary
to serve the PHA residential communities.
The
problem of providing an adequate supply of affordable housing is a
major issue in many areas of the country, and PHAs provide one of the
solutions to that problem. Yet, how can PHAs that financially depend
upon rents paid by limited income residents, although supplemented by
HUD subsidies, gain the funding to meet the upfront capital costs of
equipment needed to protect against outages much less accumulate the
extensive capital funds needed to implement comprehensive
energy-efficiency and conservation projects?
This
need is met by regulatory mechanisms that a PHA can utilize to
finance the often capital-intensive projects required to prepare for
energy-loss scenarios and address peak demand and energy
inefficiencies that can contribute to such scenarios. One of these
mechanisms is the so-called "frozen baseline" method. Using
a type of performance contracting, PHAs are able to fund energy
projects with the savings achieved through the implementation of
critical energy measures such as energy-efficient boilers and
controls while also addressing retrofit lighting, HVAC, and other
measures.
The background of "frozen
baseline" funding is that HUD pays the cost of utilities of
certain PHA residents (which could include as many as 90 percent of
the residents in a PHA). Essentially, HUD takes a three-year average
"rolling baseline" of energy usage, "freezes" it,
and continues to pay utility costs as though the PHA were continuing
to experience utility costs based upon pre-project energy use levels
following the completion of the energy project. The PHA uses the cost
difference between the frozen baseline pre-project utility use and
the reduced post-project utility use to amortize the financing cost
of the project.
As an illustration, let us
assume that the PHA's existing average energy usage and demand, over
a three- year period, amounts to $100,000 a year. For the purposes of
this example, let us also assume that HUD subsidizes the entire
amount of the PHA's utility costs. The PHA then conducts a bid
process for a comprehensive energy audit and performance contracting
agreement. It then negotiates a 12-year performance contract
agreement with the successful energy services company (ESCO) to
install measures including new boilers, HVAC, and a building
management system, which the ESCO projects to reduce energy usage in
the PHA by 20 percent, producing annual savings of $20,000 per year.
As part of the contract, the ESCO guarantees these energy savings.
Once HUD approves the contract and project, the PHA secures project
funding by a "municipal lease" financing that requires
annual payments of less than $15,000 each. Following the completion
of the project, energy usage is reduced by more than 20 percent and
the post-project energy usage results in utility costs of no more
than $80,000 per year. As part of the "frozen baseline"
process, HUD continues to pay the PHA $100,000 a year for the 12-year
term until the cost of the project is amortized. Therefore, the PHA
is able to pay the annual cost of $15,000 for the project through
savings achieved.
It is not an easy or
short process for a PHA to go from A to Z in implementing such
projects. Such energy projects for PHAs are often large and complex
and involve many steps and processes such as contract negotiations,
securing utility incentives, and the arranging of financing. PHAs
often rely on specialized consulting and professional services to
provide guidance, assistance, and support. A PHA must also comply
with complex HUD regulations. It is also reasonable to anticipate
that HUD approval and the financing process may take months to
complete. Keeping the board of the PHA informed and involved is also
important since the project cannot proceed without such approvals and
the complexity of such projects and the related financings can
require time in order to familiarize the board. Over the past year in
particular, projects have taken a substantial period of time to "put
on line" in light of the burden of the difficult municipal
market.
In such a scenario, the PHA must
look far ahead and plan carefully to ensure that mission-critical
equipment is replaced before failure or compromise and that all prior
contingencies relating to the installation of critical equipment, are
resolved so that the equipment is in place when needed.
In
a recent instance, boilers in several residential building complexes
of a PHA required replacement prior to the next heating season. Long
lead time ordering of the boilers was necessary in order to make sure
that these were installed in sufficient time, but HUD approval of the
project was still pending as the lead time was expiring. Under those
pressing circumstances, we were able to make use of a type of
contract called an agreement to proceed, to allow work to proceed on
the boiler procurement pending final HUD approval of the project. The
boilers were thereby ordered in time to be installed prior to the
onset of cold weather. The project was approved by HUD in time for
the boilers to be installed, and the agreement to proceed was
superseded by the performance contracting agreement between the ESCO
and the PHA.
This article is intended to
present only an overview of the "frozen baseline" process
which is not the only HUD process available and will not necessarily
be applicable to any particular PHA. The fact that such a project can
present challenges should not detract from looking into the
feasibility of such a project and the benefits such a project can
bring to a PHA.