Managing the Way to a Green Data Center
by Steven Yellen
February 1, 2010
 |
| Figure
1. High-density environments can create hot spots that surpass 30 kW
per rack. |
|
Tools must be used wisely.
Following
a green path, once a concept relegated to a small group of
environmentalists and the U.S. Environmental Protection Agency (EPA),
is turning into a significant activity for organizations worldwide.
And with soaring energy prices, shrinking floor space, and larger
masses of data being generated, the green data center is fast
becoming a focal point of interest.
Evolving
to a green data center and optimizing operational efficiency is a
complex endeavor. Utilizing a holistic perspective to manage the data
center infrastructure and following data center best practices can
move the process along in a step-wise manner with measurable benefits
being realized along the way. A strong data center infrastructure
resource management system can assist organizations “green” their
data centers by providing the building blocks for managing the data
center as a single entity and rolling out these best practices
processes.
The Growing Challenges
|
|
| Figure
2. Site costs will reach almost 300 percent of 1U server costs by
2012 in a best-case scenario derived by The Uptime Institute. |
|
IT
customers are consistently demanding better performance from data
centers and high reliability at lower prices. Meeting these demands
have resulted in faster servers, lower-cost storage, and more
flexible networking equipment. While technology advancements—such
as high-density blade servers—have succeeded in providing greater
performance, the operational costs associated with such improvements
have reached astronomical levels. As long ago as August 2007, Ken
Brill, founder of The Uptime Institute Inc., forecast a potential
crisis. “The benefits of [Moore’s Law] are eroding as the costs
of data centers rise dramatically,” he stated. “Increasing demand
for power is the culprit, driven by both higher power densities and
strong growth in the number of servers in use.” In fact,
predictions by a variety of industry analysts have indicated severe
problems will occur if energy efficiency is not achieved, including:
- According
to a 2008 Digital Realty Trust survey of senior data center
decision-makers, power use of data centers (average kW use per rack)
jumped 12 percent from 2007 to 2008.
- The
increase in high-density IT equipment, the cost and scarcity of
power, and the focus on the reduction of greenhouse gas emissions are
requiring new technology to meet these challenges. (Gartner, July
2009)
- In a recent survey of 100
data center operators, 40 percent reported running out of space,
power and cooling capacity without sufficient notice (Aperture
Research Institute)
|
|
| Figure
3. Total growth in electricity use from 2000 to 2005. |
|
The
increase in the number of installed servers has driven up power
consumption more than any other element within the data center. With
high-density servers filling the racks, hot spots are being created
that surpass 30 kilowatts per rack. Consequentially, many data center
managers are finding they cannot obtain enough power to distribute to
the racks or that the power utility is unable to deliver additional
capacity. To further compound the issue, the
costs associated with electricity are rising significantly.
Currently, power and cooling costs represent up to 44 percent of a
data center’s total cost of ownership. The Uptime Institute
estimates that the three-year cost of powering and cooling servers is
approximately one-and-a-half times the cost of purchasing server
hardware (see figure 2). Extending these projections out to 2012 show
the multiplier increasing to 22 times the cost of hardware under the
worst-case scenarios and to almost three times for the best-case
situations. Figure 3, developed by The Uptime Institute, maps out the
cost projections for powering and cooling average servers in a data
center (OpEx + amortized CapEx), as it relates to the cost of buying
a server.
Planting the Seeds
These
challenges are not being ignored, as corporations, utilities, and
governments worldwide are developing measures to address not only
sky-high energy bills, but also new and expanding regulations for the
disposal of IT equipment and the growing concern over global warming.
The EPA distributed a preliminary Tier 2 draft specification for
servers on September 24, 2009, and is progressing on standards for
storage and networking equipment as well. Utility companies have
begun initiating programs offering rebates for increasing energy
efficiency. A research study by Digital Reality Trust reported that
60 percent of companies expect green data center strategies to be a
part of future capital spending. A new directive in the European
Union has been established to reduce energy usage by 20 percent by
2020. Some high-profile efforts have already been instilled to
showcase green data centers—including the first “green data
center” built in August 2005 for Fannie Mae and Sun’s new data
center built in 2007.
Green Data Centers in the Making
The
first green data center was built in August 2005 for the Fannie Mae
Urbana Technology Center (UTC), an environmentally sustainable
247,000 square-foot data center and office building. The UTC has
earned a Leadership in Energy and Environmental Design (LEED)
certification from the U.S. Green Building Council. Creative design
that boosted sustainability and provided adequate support for
computers, security, lighting, and power redundancy reduced overall
energy consumption by 20 percent.
|
|
| Figure
4. Green IT awareness levels among executives worldwide. Source:
Studies show green IT awareness, but little planning, June 20, 2007,
Penn, Schoenm and Berland Associates, ItBusiness.ca |
|
Sun
built a high-profile green data center in 2007, which has resulted in
a dramatic decline in electricity use. Sun deployed new server
technology and state-of-the-art cooling system, consolidated its
Silicon Valley data centers, and halved the footprint of its
facilities—contributing to a nearly 61 percent reduction in power
consumption. Sun reduced the number of servers from 2,177 to 1,240,
but computing power reportedly increased by 456 percent, accomplished
primarily by investments in virtualization. In
addition, a survey conducted by Penn, Schoen & Berland Associates
questioned more than 400 corporate leaders from the U.S., the United
Kingdom, Canada, and China regarding their awareness of Green IT.
Although few had put any strategic initiatives in place, the vast
majority was very aware of the environmental issues (see figure
4). Confusion as to what constitutes the best
approach is one of the major reasons corporations have not
implemented a green strategy plus they say that it is not clear how
to measure whether specific strategies and technologies actually
work. There is no clear industry standard with regards to measuring
energy efficiency within data centers, but it is quite evident that a
roadmap to assist companies in these efforts is desperately
needed. A consortium of information technology
companies and professionals developed The Green Grid
( www.thegreengrid.org) in response to the lack of standards and
confusion, to promote energy efficiency, and lower the overall
consumption of power in data centers. By providing data and guidance,
The Green Grid expects to assist data center managers in making
better decisions with respect to design, planning, deployment and
day-to-day operations. The Green Grid
encourages data center managers to use one of two fundamental metrics
for measuring data center effectiveness and efficiency—power usage
effectiveness (PUE) and its inverse, data center efficiency
(DCE). PUE (also called the energy efficiency
ratio—EER—by the EPA) represents the amount of total energy
entering the data center facility divided by the power delivered (and
consumed) by computing resources. The smaller the ratio is, the
greater the amount of power entering the facility that is used
directly by computing (IT) resources. Many industry analysts have
stated that the ultimate goal is to obtain a PUE of 2; some large
companies seem to be racing to have PUEs less than 1. In order to
manage operations to the PUE ratio, data center managers and operator
must fully understand the infrastructure components affecting total
facility power—such as if the chillers and/or power are the
inefficient factors.
Steps to a Greener Data Center
|
|
| Figure
5. Decreasing PUEs represent increasing energy efficiency. Ultra
efficient facilities are achieving PUEs approaching 1.0. |
|
Without
established industry standards, what is the best way to evolve to a
green data center that is focused on energy efficiency? How do data
center managers and facilities managers understand the most cost
effective means to implement the green data center? Although there is
no single solution, there are many steps that can be taken to help
improve productivity and efficiency. Implementing data center best
practices and taking a holistic perspective to managing operations
can create a robust decision support system to monitor and measure
productivity and efficiency. 1.
Eliminate “Ghost” Servers. Approximately 8 to 10
percent of servers in many of today’s data centers have no
identifiable function. Technically considered dead with regards to
serving the organization, these servers can still haunt an
organization by consuming IT resources. These forgotten—and usually
undocumented and unprotected—pieces of equipment take up valuable
floor space, waste power, and become a ripe target for hackers.
Current estimates indicate that removing just one physical server
from service can save $560 annually in electricity costs, assuming 8
cents per kilowatt-hour. 2.
Improving Resource Utilization. Organizations must manage
a data center infrastructure according to its specific power and
cooling profiles. At the time of a facility design or build out,
organizations typically pre-determine specific operating guidelines
for racks—including power and cooling limits—in order to properly
design the power and cooling infrastructure. Currently, many
organizations lack quality information sources on power consumption
and heat output, which causes operations to run well below the
designed levels effectively underutilizing these critical
resources. Whether a data center is comprised
of high-density or low-density servers, a data center infrastructure
resource management system can assist data center managers and
facility managers design the physical layout to meet specific
capabilities, to avoid disruptions and to reach optimal utilization.
The system combines real-time measured values and manufacturer
specifications with a detailed model of the data center, enabling
organizations to “recapture” unused resources.
3.
Eliminate the barriers between IT and Facilities. In many
companies, the IT and data center facilities groups continue to
operate as two separate and distinct organizations with little
communication and interaction. As stated by the EPA in its report to
Congress, in many data centers those responsible for purchasing and
operating IT equipment are not the same as those responsible for the
power and cooling infrastructure—leading to split incentives. Thus,
those most capable of controlling the use of energy have very little
incentive to do so. A single business model where both IT and
facilities work together and let the economics drive the solutions as
well as implementing chargeback for power will be critical to harness
the power and cooling resources within the data
center.
4.
Implement standardized performance measurements. Assessing
and reporting on the energy performance—including power
distribution and power cooling—as well as benchmarking will help
data center managers better understand the relationships between
power distribution and consumption.
In
energy-efficiency management, measurement goes far beyond just
calculating the ratios, but truly understanding what is behind the
ratios. Better analysis, planning, and execution of a green data
center can only occur when the underlying relationships are
understood and the data center is managed from a holistic
perspective.
5.
Evaluate investment alternatives to upgrade the data center
equipment. Many data centers in operation today were built
prior to 2002 and did not include design specifications to support
high-density operation and deliver power and cooling to racks
operating at over 2 kilowatts. By assessing the needs of the
organization, evaluating design alternatives to dramatically reduce
power requirements within the infrastructure and applying innovative
technologies, significant computing power per kilowatt can be
recognized. Just replacing legacy equipment with newer,
energy-efficient models can reduce the overall power and cooling
requirements of a data center.
Conclusion
Following
a greener path has become much more than an altruistic endeavor.
Organizations are focusing on developing green data centers in order
to reduce the exorbitant power and cooling costs as well as improve
operational efficiency. It is quite apparent that the need to
construct and operate green buildings will be more and more
important—for shareholder value and for the environment. New and
emerging tactics and technologies to develop solutions that address
today's critical business needs and environmental requirements will
deliver economic benefits in an environmentally sound manner, while
addressing power and cooling issues in the data center. Decision
support systems can assist data centers in becoming “greener” by
allowing data center managers manage the physical infrastructure from
a holistic perspective and in an integrated process.
|