Out of Power, Out of Cooling
by Dr. Kenneth Uhlman Uhlman P.E.
James VanderPas
April 1, 2009
|
|
| Figure 1. Legacy volume data center with 4 kw/rack |
|
Solutions for high-density data centers
This article is based on a white paper
prepared by Eaton and UTC Power. The full white paper can be downloaded here.
|
|
| Figure 2. Blade server data center |
|
While new technologies that improve IT
utilization, such as blade servers and virtualization, solve some
issues, they also create new ones. Increased power densities free up
floor space in the legacy data center, but they also quickly use up
power and cooling. This results in underutilized raised floor space.
This is especially true within data centers located in markets where
incremental utility power is not readily available. The latest
generation of service-based applications has minimum response-time
criteria, which increases the importance of the physical location of
data centers hosting those applications and exacerbates the shortage
of power and space in already constrained markets. With
the U.S. Environmental Protection Agency forecasting that energy
consumption by servers and data centers in the U.S. will double in
the next 5 years, organizations are now at a tipping point. They must
develop strategies that meet their growth objectives, increase energy
efficiency, and incorporate new technologies while maintaining or
increasing system availability.
Data Centers
Historically, many data centers used
volume servers in a dedicated, single-application model, meaning they
could not reprovision themselves with multiple software applications.
For practical purposes, these servers were also physically
constrained to their original racks. This resulted in average server
utilization rates in the 10-20 percent range. Many of these servers
were dual corded, which enabled them to operate on an “A” or “B”
power system for increased availability. This architecture led to
very inefficient power systems, since an idle server still consumes
approximately 50 percent of its full load power.
Similarly,
UPS systems in a dual-bus power distribution configuration are loaded
less than 50 percent to enable them to assume the full data center
load. At these utilization rates, legacy UPS systems are typically
less than 85 percent efficient, resulting in energy losses and
additional stranded capacity. Inefficient legacy computer room air
conditioning (CRAC) systems compound the inefficiencies since they
typically run at 100 percent, regardless of true heat load.
As a result, such data centers supply only
one-third to one-half of input power to IT loads and the majority
supplies ancillary support systems. Figure 1 shows a data center with
a 1-megawatt (MW) utility substation and 400 kilowatt (kW) of UPS
output power feeding a server farm of servers rated at 4 kW/rack,
which is a typical density.
To increase
server utilization and flexibility while reducing IT costs,
organizations are incorporating blade servers and virtualization.
These technologies enable rapid server hardware deployment and the
ability to reprovision applications and services from one server to
the next anywhere on the network within minutes. Power densities in
these facilities easily reach 25 kW/rack. Densities in the range of
50 kW/rack are on the horizon. Figure 2 shows the legacy data center
from figure 1 reprovisioned to house 25-kW/rack blade servers. Each
row in the redesigned data center contains 10 racks, for a total of
250 kW. After two rows, the data center is out of UPS power and
cooling capacity.
Freeing Stranded Capacity
Liquid-cooled racks and in-row cooling
solutions free some stranded capacity. High-efficiency power supplies
can further reduce power and cooling loads. High-efficiency,
double-conversion ac UPS systems operate at 97 percent efficiency
across the entire load spectrum, while providing maximum protection
(see figure 3). These reduced losses, coupled with the reduced
cooling load, may free up to 25 percent of the UPS system for IT
purposes. High-efficiency transformers in power distribution units
add to the savings.
|
|
| Figure 3. High-efficiency UPS systems |
|
Addressing inefficient cooling
strategies and technologies may result in incremental cooling
capacities being freed. Traditional computer room air conditioning
(CRAC) systems met the cooling demand in legacy data centers but may
not adequately or efficiently cool higher-density facilities. Cooling
alternatives include hot aisle/cold aisle isolation, self-contained
cabinets, and rear-door heat exchangers. These technologies place
cooling directly at the heat source, using less energy and freeing
cooling capacity.
Incremental Power and Cooling Solutions
Adding utility substations, generators,
and cooling units is seldom practical due to the complexity involved
of duplicating power and cooling to existing systems. For many
facilities, on-site combined cooling, heating and power systems
(CCHP) may be a cost-effective solution, especially compared to
building a new data center. Prefabricated microturbine or fuel cell
solutions enable data center operators to:
- Add
incremental power and cooling quickly.
- Generate
electricity at 40-60 percent below the cost of equivalent
grid-purchased energy.
- Obtain free
cooling from absorption chillers.
- Augment
absorption chilling with sidestreaming series flow configurations,
allowing the absorption machines to divide the work load with
high-efficiency, VFD-controlled electric chillers. This results in
expanded cooling production at reduced energy consumption (in a range
of 0.15-0.35 kW/ton). Such technology is under development at UTC
Power under the trade name Active Redundant Cooling.
- Divert
surplus thermal energy to heat non-data center hydronic or ducted-air
heating systems.
- Mitigate the risk of
rising energy prices by locking in using various natural gas supply
contract mechanisms.
- Design the on-site
generation system with redundancy that improves the overall
availability of the data center.
- Capitalize,
lease, or use third-party companies to outsource the operation and
maintenance of the CCHP system.
|
|
| Figure 4. A CCHP system with four 200-kW microturbines |
|
Figure 4 shows a CCHP system with four
200-kW microturbines providing nominal 750 kW of net electricity and
535° F waste heat fed into two absorption chillers that can deliver
about 350 RT nominal output of chilled water. Grid paralleling is
handled by onboard system components, eliminating complex wiring. The
microturbine generators feed the 480-Vac electrical system through
any open 480-V three-phase breaker position. An
absorption chiller captures the turbine exhaust to produce cooling.
In a perfectly sized system, the cooling output of the CCHP system
will eliminate 95-100 percent of the electric power required to run
conventional cooling equipment. In extreme ambient conditions, the
conventional equipment remains available to augment the cooling
produced by the CCHP system. Therefore the total available cooling is
the sum of conventional cooling and CCHP system cooling. For larger
data centers, absorption chillers can be integrated with Active
Redundant Cooling.
Thermal priority is given to cooling;
however, any remaining surplus energy can simultaneously produce hot
water at 175°F (79.4°C), or surplus exhaust energy can be diverted
to create steam at up to 100 psi, if applications where heating is
necessary For new data centers, CCHP systems
can be integrated into the design to achieve 99.9985 percent critical
load availability in concert with the normal utility source, which
reduces some need for diesel generators. Cooling redundancy can be
completely eliminated since CCHP systems designed for
grid-independent load service typically provide 2N to 3N of
mission-critical cooling capacity. Equipping
the CCHP system for dual-mode operation enables it to make use of
surplus power and thermal capacities. Dual-mode allows the CCHP
system to parallel the utility under normal conditions. Through
paralleling, surplus power can flow to the entire data center or to
the surrounding building and even to be exported to the grid.
Dual-mode allows electric base loading so the system runs constantly
at 100 percent electrical output. When base loaded, turbine exhaust
mass flow is at its greatest, maximizing the production of useful
cooling (or heating). In emergencies,
dual-mode controls activate the fast-transfer capabilities of the
turbine system, switching the critical load to be powered only by the
CCHP system. Cooling systems are designed to ride through the
momentary transfer outages and be fully operational during grid down
conditions. With data center retrofits, these
same capabilities can be achieved provided the CCHP system is also
sized for the full capacity of the IT load expansion, with its own
inherent redundant power and cooling. Just as with new facilities,
system redundancy can be put to full use through Dual -mode
configurations. Where the utility does not have capacity for
expansion, CCHP becomes the “utility,” and conventional backup
systems provide the contingency for high-tier operation.
Microturbine systems are also environmentally
green compared to central power plants, producing less CO2 and
nitrogen oxides as well as conserving water.
Financial Analysis
|
|
| Figure 6. Side-by-side comparison of data centers with and without CCHP systems being utilized. In this example a smaller CCHP system increases the available power and cooling for a 400-kW data center. |
|
A CCHP system sized to match the
cooling requirement will provide the shortest payback and best
efficiency (see figure 6). For example, each megawatt of IT load
normally requires about 350 tons of cooling. Two PureCell Model 400Ms
with ARC matched to a 350 ton cooling requirement would supply 100
percent of the cooling. This eliminates the need for conventional
compression chilling. By displacing 350 tons of conventional
chilling, metered power drops by 250 kW. The prime movers
(generators) will displace about 750 kW of metered power. The total
reduction in metered load will total 1,000 kW. Total displacement is
often slightly more, given the displacement of transformer losses
upstream of the point of injection. At 1,000-kW displaced energy, the
CCHP system is 100 percent base loaded, both electrically and
thermally (the ideal). Cost savings depends
on the relative cost of fuel versus electric power purchased from the
utility. This cost difference is often called “spark spread. The
table in the sidebar shows savings at various spark spreads and
illustrates the importance of applying these systems where the cost
differential is greatest (see the sidebar). Such
a design does not capture costs for data center reliability and will
not eliminate the need for diesel or chiller redundancy. If the grid
is down, the system would separate from its grid connection and pause
while traditional backup systems handle the emergency.
Sidebar: Fuel-Cell Solutions
Fuel cells augmented by combinations of absorption chilling and Active Redundant Cooling are a viable displaced energy solution. These combinations allow thermal-to-power ratios to match to datacenter loads. Fuel cells in the 400-kW class are expected to be much lower in cost ($/kW) compared to earlier 200-kW versions. Additionally, improvements in technology have increased cell stack life to10 years so they can last for 20 years with an overhaul at the end of year 11. These improvements, the tight integration of the balance of plant, and remote monitoring capabilities have driven down theO&M cost of a fuel cell by about a half of previous costs. In part because of their excellent emissions performance, fuel cells show good promise for data center operations, especially as data centers become increasingly environmentally and ‘green’ conscious. Each 1000kW of displaced power from fuel cells can result in almost 2000 metric tons of annual avoided CO 2 compared to the baseline average for fossil fuel plants in EPA sub-regions where CCHP is most often applied.
Applying Spark Spread
The table illustrates the potential annual savings from various spark spreads for an two by 400-kW PureCell system with an Active Redundant Cooling system in concert with absorption cooling, assuming a gas price of $11.00/MMBtu and a system-installed price of about $4.1M. The comparison is to the time temperature weighted performance of electric compression chilling (annualized at 0.74 kW/ton average). Using Newark, NJ, ambient conditions, this installation produces a time-weighted annual average of about 800-kW of electricity and up to 600 tons of cooling or 1010 kW of continuous total power displacement. Such a system would be integrated to a data center with at least 1.0 MW IT load or greater. Considering the state and federal incentives that are now available under TARP and ARRA, the net cost can be under $2.0 M and resulting paybacks under 3.0 years! For a detailed list of these state-by-state incentives, please refer to www.dsire.org.
|